1x36.0M + 2x24.0M composite girders for ROB, Bareth as per C.A. No. DyCE(br) line/ BPL/2017/04 dt. 30-10-17 (Completed).
Rs. 6.50 Crores
12
1x36.0 + 2x24.0M composite girdes for ROB Damoh for M/s. Ajay Protech, Mehsana. Completed March, 2018.
Approx..1.0 cr (labour basis)
13
1x36.0M + 1x24.0M composite girders for ROB, Bavaria Kalan for M/s Rachna Construction. Completed May, 2018.
-do-
14
2x36.0M + 1x30.0M skew composite girders for M/s. CDS Industries Ltd., New Delhi for Singarcholi bridge, Bhopal (Completed).
-do-
15
1x36.0M span composite girder for ROB, Shridham for WCR/Br/JBR, as per C.A. No. WHQ/Br/Const ROB at 294/JBR dt. 15-03-18. (Completed).
Rs. 5.49 Crores
16
Fabrication of 27x30.5 mtr Composite Girder spans of M/S Binorilal Meghani for West Central Railway at Mohanpura Dam Near Biora City : (Completed) July 2021.
Rs. 4.0 Crores
17
FAbrication of 2x30.5 mtr & 2x36mtr Composite ROB GIRDERS spans for M/S Goyal & Company (Expected Completion OCT 2021).